The project “Hydro Pumped Storage in Amfilochia” is the largest investment in energy storage in Greece.
With a total installed capacity of 680 MW (production) and 730 MW (pumping), the project consists of two independent upper reservoirs (Aghios Georgios and Pyrgos) and a common lower reservoir, Kastraki Lake.
The project’s objective is the energy storage and the maximization of renewable energy (RES) penetration in the energy production mix in Greece.
Annual energy production: ~ 816.00 GWh
The RRF contribution amounts to € 250 million
Top 100 recipients:
- ΤΕΡΝΑ ΕΝΕΡΓΕΙΑΚΗ ΑΝΤΛΗΣΙΟΤΑΜΙΕΥΣΗ ΜΟΝΟΠΡΟΣΩΠΗ ΑΝΩΝΥΜΗ ΕΤΑΙΡΕΙΑ
Additional media:
- Reference
- Component 1.1, Measure 16926 in the GR Recovery and Resilience Plan
- Project locations
- Greece
- EU contribution
- €250 000 000
- Project website
- https://www.terna-energy.com/acivities/...