The Recovery and Resilience Plan (RRP) supports the development of a battery energy storage system at the Fundão Solar Power Plant, with an investment of €3.1 million. The project involves the installation of lithium-ion batteries with 42.3 MW of power and 80.49 MWh of storage capacity.
This system enhances the efficiency of renewable energy production by storing surplus energy and releasing it into the grid when needed, improving supply stability and flexibility. It also provides essential services to the national electricity system, supporting demand balancing and grid reliability.
Funded under Component C13 – Energy Efficiency and Renewable Energy, the project contributes to accelerating the energy transition, reducing carbon emissions and strengthening the resilience of Portugal’s energy infrastructure.